Projects :: Electrical
Click Here to view Electrical Images
| Project Name: |
Construction of 33kV Feeder 738 from Ashfield to Strathfield substations |
| Location: |
Ashfield to Strathfield, Sydney NSW |
Client: |
Rail Corp |
| Project Status: |
Current |
Completion Date: |
Oct 07 |
| Size / Complexity: |
Challenging |
Value: |
$1 - $5 million |
| Project Description: |
Construction and installation of a 33kV feeder within road reserve and rail corridor. |
| Project Name: |
Energy Australia Underground Distribution Panel |
| Location: |
Sydney Metropolitan, North Sydney and CBD and Hunter Region NSW |
Client: |
Energy Australia |
| Project Status: |
Current |
Completion Date: |
On Going |
| Size / Complexity: |
Average |
Value: |
Various |
| Project Description: |
Construction of underground electricity conduits and cables for a contract period of 2 years with option of additional 4 year contract. |
| Project Name: |
Design and Construction of New 11kV Feeder to the PA Hospital |
| Location: |
Brisbane, Qld |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Sept-05 |
| Size / Complexity: |
Average |
Value: |
$5000,000 - $1 million |
| Project Description: |
Trenching and installation of conduits and 11kV cables. |
| Project Name: |
Scrub Road Substation |
| Location: |
Carindale QLD |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Dec-05 |
| Size / Complexity: |
Above Average |
Value: |
$1 -$5 million |
| Project Description: |
Install 33Kv underground cables from Belmont Bulk Supply Substation to Scrub Rd Substation |
| Project Name: |
South Coast Distribution Area QLD - Contract QL40 |
| Location: |
Nerang, Hope Island, Yatala QLD |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Dec-05 |
| Size / Complexity: |
Average |
Value: |
$1 - $5 million |
| Project Description: |
Trenching & Installation of Conduits & 11kV Cables |
| Project Name: |
Zillmere |
| Location: |
Brisbane QLD |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Dec-05 |
| Size / Complexity: |
Average |
Value: |
< $500,000 |
| Project Description: |
Trenching & Installation of Conduits & 11kV Cables |
| Project Name: |
Alexandra Headlands |
| Location: |
Sunshine Coast - QLD |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Nov-05 |
| Size / Complexity: |
Average |
Value: |
<$500,000 |
| Project Description: |
Trenching & Installation of Conduits & 11kV Cables |
| Project Name: |
Varsity Lakes QLD |
| Location: |
Gold Coast - QLD |
Client: |
Energex |
| Project Status: |
Complete |
Completion Date: |
Nov-05 |
| Size / Complexity: |
Above Average |
Value: |
$500,000 - $1 million |
| Project Description: |
Trenching & Installation of Conduits & 11kV Cables |
| Project Name: |
Springwood QLD |
| Location: |
Brisbane QLD |
Client: |
Energex |
| Project Status: |
Current |
Completion Date: |
Nov-05 |
| Size / Complexity: |
Average |
Value: |
<$500,000 |
| Project Description: |
Design of conduit plans, Trenching & Installation of Conduits & Cables |
| Project Name: |
Coomera QLD |
| Location: |
Gold Coast - QLD |
Client: |
Energex |
| Project Status: |
Complete |
Completion Date: |
Aug-05 |
| Size / Complexity: |
Average |
Value: |
$1 - $5 million |
| Project Description: |
Trenching & Installation of Conduits & 11kV Cables |
| Project Name: |
Williamtown RAAF |
| Location: |
Newcastle NSW |
Client: |
Energy Australia |
| Project Status: |
Complete |
Completion Date: |
Jun-05 |
| Size / Complexity: |
Above Average |
Value: |
$1 - $5 million |
| Project Description: |
11kV & 33Kv Feeder to Williamtown RAAF Base, ASS Soils and Watercharged Ground |
| Project Name: |
Merewether Sts & Newcastle CBD |
| Location: |
Newcastle NSW |
Client: |
Energy Australia |
| Project Status: |
Complete |
Completion Date: |
May-05 |
| Size / Complexity: |
Above Average |
Value: |
$1 - $5 million |
| Project Description: |
Construction of a New 33Kv Underground Feeder between Merewether Sts & Newcastle CBD |
| Project Name: |
Picnic Point to Haymarket |
| Location: |
Sydney NSW |
Client: |
Transgrid - Mitsui (AUS) Pty Ltd |
| Project Status: |
Complete |
Completion Date: |
Sep-04 |
| Size / Complexity: |
Challenging |
Value: |
< $50 million |
| Project Description: |
Underground Electrical Cable Installation 27km of 330kV from Picnic Point to Haymarket |
| Project Name: |
Wattle Street Haymarket |
| Location: |
Sydney NSW |
Client: |
Transgrid |
| Project Status: |
Complete |
Completion Date: |
May-04 |
| Size / Complexity: |
Challenging |
Value: |
$1 - $5 million |
| Project Description: |
Transgrid Cable Tunnel Wattle Street Cable Bores, Haymarket |
| Project Name: |
Hyde Park |
| Location: |
Sydney NSW |
Client: |
Energy Australia |
| Project Status: |
Complete |
Completion Date: |
May-04 |
| Size / Complexity: |
Above Average |
Value: |
$1 - $5 million |
| Project Description: |
Construction Smart Poles |
|